Preliminary Project Schedule
Task 1 – Project Initiation
January – February 2008
Task 2 – Public Consultation
January – August 2008
Task 3 – Design Report
January – February 2008
Task 4 – Project Design
February – September 2008
Task 5 – Permitting
May – July 2008
Task 6 – Right of Way Acquisition
May – August 2008
Task 7 – Bid Project
September – October 2008
Construction
December 2008 – December 2009
Completion
2010