Preliminary Project Schedule

Task 1 – Project Initiation
January – February 2008

Task 2 – Public Consultation
January – August 2008

Task 3 – Design Report
January – February 2008

Task 4 – Project Design
February – September 2008

Task 5 – Permitting
May – July 2008

Task 6 – Right of Way Acquisition
May – August 2008

Task 7 – Bid Project
September – October 2008

Construction
December 2008 – December 2009

Completion
2010